Overview - EIS Timeline
 

EIS Timeline:

  • Agency Scoping Meeting   September 14, 2004

  • Public Scoping Meeting in Staten Island, NY   October 5, 2004

  • Public Scoping Meeting in Elizabeth, NJ   October 6, 2004

  • Close of Scoping Comment Period   November 5, 2004

  • Technical Advisory Committee (TAC) Meeting #1 at USCG Offices, March 3, 2005

  • Environmental Task Force (ETF) Meeting #1 at USCG Offices, March 3, 2005

  • Stakeholder Committee (SC) Meeting #1 in Staten Island, NY, March 24, 2005

  • TAC Meeting #2 at USCG Offices, June 1, 2006

  • ETF Meeting #2 at USCG Offices, June 1, 2006

  • SC Meeting #2 in Elizabeth, NJ, June 15, 2006

  • Public Open House, Elizabeth, NJ, June 27, 2006

  • Public Open House, Staten Island, NY, June 28, 2006

  • Special Combined TAC/ETF Meeting at USCG offices, September 6, 2007

  • ETF, TAC, Stakeholder and Public Meetings, estimated late Fall 2008

  • Draft EIS and Public Hearings, estimated Winter 2008/2009

 
HOME USCG Logo
 
GBMP EIS Overview Link
  Steps in the Process
  NEPA Requirements
  Notice of Intent
  Scoping Process
  Purpose and Need
  Goals
  Preliminary Alternatives
  Potential Issues
  Refined Project Alternatives for DEIS Analysis
  Study Area
  EIS Timeline